The following information applies to the period of June 6-12:
Due to utility work, Musser Street will be closed between Carson Street and Curry Street on Thursday at 7:30 p.m. The road is expected to reopen at 5:30 a.m. on Friday. Once Musser Street has been reopened, a lane closure with flagger control is expected throughout the remainder of the day.
Sidewalk improvements will continue along Long Street between Molly Drive and Saliman Road. Minor delays are possible and JAC bus stops in this area may be temporarily closed.
There will be shoulder work at the intersection of Fifth Street and Butti Way. No lane closures are expected.
Clearview Drive is closed between Edmonds Drive and Line Drive for construction on the next phase of the Nevada Department of Transportation freeway project. Detours are marked. The road is expected to reopen by November.
For more information, call Patrick Pittenger at 887-2355 Ext. 7396.